The Melksham, Calne and Chippenham Branch
of the
 Wilts & Berks Canal Trust
 
   

Links

Home

What's On

MCC News

Meeting Minutes
Features

Press Releases

Pictures

Branch Officers

Contact us

 

Canal Map

 

Trust Website
Join the Trust!
Work parties and Restoration
 
Work parties are held on second and last Sundays
For Dates and Location click "What's On " link
 
Additional work parties may be held as required.
 
Please check with the work party organiser before attending
 
Click here to see Latest  Work Party Report

Or here to see Previous Work Party Reports

Or here to see Annual Review 2009/2010
 
Please see "What's on" link for Work Party Dates
 
 
 
X

 

 

 

Working Party Report — June 2010

We have held 16 Work Parties (including today incidentally) at Pewsham since the AGM on 11th of June. Most of these have been daily sessions at the spillweir and driving heavy 4WD dumpers carrying excavated material away from the canal where our contractor has been working. These daily sessions started on the 5th July with the start of the dredging and have been continuing without a break since then.

At the spill weir a half dozen of us have been working on its repair which has come on rapidly. The periphery wall is about 90% complete which includes an extension to the discharge flume. This will prevent further erosion of the stream bank and enable us to replace the lost soil. Two more day’s work will see this finished. All that then remains is the construction of the weir wall, on which I am seeking some guidance, and the discharge benching. Both comprise considerable bricklaying and will extend the brick recovery and preparation work.

Initially the re-watering of the canal will be at a reduced level and to achieve this the spillweir will have to be adjustable, built rather like a miniature stop plank where we can add planks to raise the level as our confidence in the water tightness increases—or even remove them should there be a problem. Following the success of the re-watering some mechanical device will then be mounted on the spill weir structure to drain the canal if required.

Unfortunately the work on the spill weir has been temporarily halted as the restoration of Cocklemore Brook Culvert has become critical with the onset of the present unsettled weather. The team will start work on the culvert on Monday 19th July and will work daily until the brick roof of the culvert has been completely rebuilt. We have Robert Brotherston coming to help us again on the weekend of 24th and 25th July when, with luck, we may be ready to work on the wing walls and head structure.

The dredging has progressed well beyond expectations due to the dry conditions and to the seizing of the opportunity that the dry weather has provided. The bulk of the initial dredge now extends from Double Bridge to the stream that entered at the north side of Triangle Wood. A section at the winding hole has been left un-dredged due to the presence of Wessex Water pipes, some of which, we know are above bed level and will need lowering. Another section in the Meadow is also un-dredged for operational reasons. The dredged bed is now level with that of Double Bridge invert and the shortcomings of the cycleway built on the remains of the towpath are plain for all to see. Much raising has to be done if the canal is to have any water in it and this will use a significant amount for the dredged material. A great saving in the cost of importing embankment material.

During June our volunteers, worked a total of 430 man-hours which amounted to £6,138 in volunteer value matched funding.

You may be not be surprised to know that so far this month we have worked 636 hours which is currently valued at £9,452. Look out for July’s figures.

Douglas Harris

Return to top
   
 
Y

 

 

 

  Annual Report of  Working Party for 2009/2010

The Branch Work Party Team have enjoyed another productive year with the workforce exceeding 20 persons on several occasions. With such large turnouts the progress was impressive. Most of the work took place at Pewsham where we worked over 40 occasions and on other sites over 16. These other sites included Calne where scrub was cleared, with the help of Kent & East Sussex canal Recovery Group (KESCRG), Forest Farm and the A4 Crossing at Pewsham Village. Here a brown official sign depicting the Wilts & Berks Canal was erected by Wiltshire Council.

Pewsham

In July we hosted a week’s camp from Waterway Recovery Group. Here they carried out clearance work in Top and Middle Locks but it was a massive task and they have left plenty for us to do.  Preparatory work was carried out on the entrance portal of Cocklemore Brook Culvert which the MCC Workparty Team plan to complete during the next few weeks.

Several large trees that were growing near or on canal structures have been felled using tree surgeons in some positions where potential collateral damage had to be avoided. The remaining stumps were left long so that their ultimate removal was made easier. This was far removed from reality. The stumps were huge and took the team several weeks to extract using all of our winching gear and muscle leaving massive holes where once the trees stood. These stood in the way of our dredging plans for this year including the restoration of the Spill Weir below Bottom Lock. Rebuilding work of the Weir is well underway and is due for completion before stage two dredging—Triangle Wood to Bottom Lock. The canal bed for Stage 1 dredging (Triangle Wood to Winding Hole) has been cleared of trees and their roots and the masonry of Triangle Wood Culvert repaired.

We now have a secure lockup steel cabin located at Top Lock thanks to the efforts of Dave Maloney, where we now keep our building materials, hand tools and scaffolding. This saves a lot of work getting material and tools to site.

Most of the Pewsham Section has been mowed but the section south of Double Bridge remains. It is hoped to complete this tomorrow.

Forest & Queenfield Farms

The whole canal at Forest & Queenfield Farms was mowed at the end of September last year. This improved the canal’s appearance then but I expect it is well overgrown again by now. Such is the nature of things.

Calne

We have had a bit of a set back with our plans for the restoration of the Calne Branch. Our request to the Environment Agency for an extraction licence from the River Marden was granted with a maximum limit of 14 Lts per minute. This limited amount of water is unlikely to be sufficient to keep the branch in water let alone becoming a major feeder for the main line at Stanley. Because of the restriction in extraction and the fact that the water level in the Marden was not going to be raised CARP thought the expense of laying a pipe through the Town Lock was not justified. Their preferred option with their funding was to commission a replica canal boat to be set in the lock chamber as an illustration of what the lock used to look like. I prefer restoration to interpretation but without the money we have to concentrate on the main line of the canal rather than branch lines. The work started last December on Mrs Sutton’s land will be completed and rewatered as planned.

Attendance at work parties has remained high at a steady 20 on major events, with a maximum of 21 on some occasions. Recruitment also remains good with several promising volunteers joining us over the past year.

We have held over 57 work parties since the last AGM, clocked up 4635 man-hours of work and travelled over 9037 miles to attend the work.

This activity is evaluated as £63,727 in Volunteer Matched Funding.

Well done again everybody.

Douglas Harris

Return to top