The Melksham, Calne and Chippenham Branch
of the
 Wilts & Berks Canal Trust

Back

Previous Work Party Reports

 

 

Working Party Report — September 2011

Members of the Work Party have been involved in 10 events since the last Branch Meeting on 9th August. Four of them were a 4 day effort to complete the exit portal of Cocklemore Brook culvert which we managed on Monday 15th August in which we were finally successful. Robert Brotherston came down from Exmouth to help us with the portal arch which I must say looks very professional.

Another bench seat was erected. This time in the Meadow, one more to go—probably after the final dredging has been completed. Then on the weekend of 27/28 of August the Branch supported the Chippenham River Festival with boat trips using Willow and Damsel Fly. On the same Sunday 10 members of the work party were working at Pewsham landscaping the area around the Cocklemore Brook culvert exit.

Finally on the 11th September the team started work on renewing the waterproof membrane on Double Bridge which had not been too successful. The plan was to excavate more of the soil above the arch, lay a complete membrane over the whole area and back fill.

During the month of August the Work Party worked a total of 665 man-hours which amounted to the sum of £11,002 in volunteer value matched funding.

 Douglas Harris

Return to top
 

 

Working Party Report — August 2011

Members of the Work Party have been involved in 7 events since the last Branch Meeting on 12th July. These were mowing sessions at Calne (3) Forest & Queenfield Farms (run by Dave Maloney) and Pewsham, where the team started work on the exit portal of Cocklemore Brook Culvert. We had just one main work party since the last Branch Meeting, although we held the normal two in the month. Finally we were at the Melksham Carnival on Saturday 16th July with ‘Willow’ running Boat trips. We had difficulty in recovering the boat after the event as the end of the slipway was about 9” above the water level. Unless an improvement can be made to make it possible to launch and recover our boats safely it was felt that we could no longer support Melksham river events.

Attendance at the main work parties continues to be impressive but the mid-week events are often less than adequately supported which makes it a struggle to keep on top the maintenance work. 

On the 31st July we had an attendance of 17 volunteers so several tasks were completed during the day in addition to the work on Cocklemore Brook culvert. These included erecting a donated bench seat which was erected near the culvert at Triangle Wood, maintenance of our dumper trucks and you’ve guest it—mowing. We have mowed the bypass path through Double Bridge Meadow so many times this year that the public are beginning to use it as an alternative to the towpath, due to be closed during the towpath raising works later this year.

We tried to progress the work on Cocklemore Brook culvert following the work party, but we were short handed on the first occasion (1st August) then on the second (5th August) we were flooded out by the sudden rise in water level at midday which we were unable to cope with. Most of the work done in the morning was inundated and it was impossible to continue for the rest of the day. I doubt that we would have controlled the water level even with an additional 4” pump. Apparently there had been heavy rain on Naish Hill on the day before, surprisingly, not on the canal at Pewsham. This rain apparently was responsible for the water to rise at the canal culvert some 24hrs later. We are working on the culvert again this weekend starting on Friday. Maybe we will be third time lucky.

During the month of July the Work Party worked a total of 468 man-hours which amounted to the sum of £6,256 in volunteer value matched funding.

 Douglas Harris

Return to top
 

 

Working Party Report — July 2011

Members of the Work Party were active again for another 11 days since the last Branch Meeting. Most of the activity was spent at Pewsham on the rebuilding of the Waiting Wharf by Bottom Lock. There were two main work parties during the month with 16 and 18 members attending respectively. Clearly the turnout remains impressive. The remaining sessions were the activity of our retired members who must be congratulated on their efforts in maintaining the momentum of the projects.

The wall has now been completed except for the coping course which was deliberately omitted at this stage as it was feared that it could be damaged during the adjacent dredging. We then have a challenge to complete this brickwork afterwards but before the waters arrive. This was remarkable progress as the wall is over 35M long, about 1M high and was started by a visiting group of volunteers from KPMG on 14th April. The Work Party started work during the Sponsored Walk on the 2nd May as a demonstration of mass manual digging mainly for the entertainment of the walkers.

As we had a good workforce last Sunday the wall was backfilled to completion with the excavated clay that had been dug out from the foundations. The backfilling had been carried out progressively during the building work, but this was now the opportunity to puddle. We had a big pump and 50M of 2” hose and thought the job would be easy! However the communication between the end of the hose and the pump was not good. The hose, at full bore, was difficult to handle and somehow more was ‘watered’ than intended—including our bricklayers, who were adapting an older adjoining wall by the spillweir, some spectators and ‘Yours Truly’. In the end the job was completed successfully and the puddled clay proved to be watertight albeit, at this stage, in the opposite direction.

The group pumping out Cocklemore Brook Culvert, with an even bigger pump were also successful in clearing water from the culvert exit structure. This was necessary so that we could inspect the foundations and start the restoration process. The inspection revealed that there was less work to do than expected, only about 1M of culvert roof to be rebuilt and no wing walls of substance. There will however be some internal brickwork to be repaired. This can be carried out at the same time as the external works but will be dependant on fair weather as the brook can flow very fast following heavy rain.

All in all we have had a successful month.

During June the Work Party worked a total of 481 man-hours which amounted to the sum of £5,763 in volunteer value matched funding.

 Douglas Harris

Return to top
 

 

Working Party Report — June 2011

The Work Party had another busy month in May with 16 days (19 since the last Branch Meeting) when Wilts & Berks activity took place. Much of it was taken up with boat repair, this time it was Damsel Fly that received some sprucing up after spending a couple of months in icy water at Swindon.

You may have guessed that the drive to get the trip boats into shape was to have presentable craft for the Calne Bunny Hunt on Easter Saturday and the Sponsored Walk on the May Bank Holiday Monday. Also for the Chippenham Folk Festival, on the Spring Bank Holiday, we had both in use. Willow was modified, earlier last year, to accommodate the 24volt battery in the bow as the combined weight of the electric outboard motor, battery and helmsman, at the stern, gave the craft a certain sinking appearance. The trim is just about right now with the improved weight distribution. Recently purchased new batteries gave Willow a significantly longer range.

We had a successful time at the Chippenham Folk Festival running by both boats throughout the day. At times business was brisk with people waiting for a trip on the next available boat. Monday morning was disappointing with almost continuous drizzle discouraging all but one determined passenger. The afternoon was an improvement with the boats in use most of the time. Our takings over the weekend amounted to £661.80 gross with £108.73 in expenses for fuel and a fee to the Festival. The volunteers at the Festival worked a total of 274 man-hours to manage the Boat Trips and the Information Tent. These events are good for publicity and there was a lot of interest in our project shown by the general public.

We had a successful day at Pewsham for the Sponsored Walk. We celebrated the official opening of the newly re-watered section at Squirrel’s Rest by Duncan Hames, Member of Parliament for Chippenham. We also had the official unveiling of the newly restored Spill Weir. For the latter we managed to fill the canal side of the weir, blocking the culvert to the canal with clay and a circular diaphragm of plywood. The Deputy Chairman of Chippenham Area Board Mr Mark Packard was invited to open the weir penstock which produced a mini tsunami down the chute into the leat  leading to the brook whence the water had earlier been extracted.

The Wharf Wall trench between Bottom Lock and the Spill Weir was started on the day of the Sponsored Walk to demonstrate restoration in progress. Many of the walkers noticed the good progress made during the day on their return. The trench was fully excavated in just three working days followed by the laying of the concrete foundation on Friday 20th May. Since then we have had four sessions of block laying. Last Sunday was a disappointment as heavy rain dismissed any chance of laying blocks but we managed to concrete in a significant number of reinforcement bars and clear much of the excavated stone. It still surprises me what a large (16) turnout can achieve even in adverse weather conditions.

During the month of May the Work Party worked a total of 948 man-hours which amounted to the sum of £11,129 in volunteer value matched funding.

 Douglas Harris

Return to top
 

 

Working Party Report — May 2011

The Work Party have been busy on some 17 occasions since the last Branch Meeting. Much of the activity has been with a just a few volunteers working on boat repairs and finishing work at Pewsham in preparation for major events. Of the main workparties, we have held three, since the last Branch Meeting; all at Pewsham. Other events have been boat trips at Calne on Saturday 23rd April in support of CARP’s Bunny Hunt in Castlefields Park. This was the inauguration event for the rebuilt Chaveywell Wharf that was completed on 24th March with the fitting of an Oak fender on the canal side.

The Spill Weir at Pewsham was finally completed with the painting of the Traditional Estate Fencing on Wednesday 27th April when 8 volunteers turned out to help. The fencing was erected on Sunday 17th April. It was a bit of a challenge as it had to be shaped to fit the perimeter of the structure. Also the Penstock was installed during the same day. I am always amazed what a strong workparty (14 people) can do in just one day.

An interesting job at the Spill Weir followed the next day when we tested it for leaks. Water was borrowed from Cocklemore Brook and with the aid of a 2in pump and some borrowed pipework we filled the canal side of the weir in just over 10 minutes. Yes, we did have a few leaks which were identified before the water was released. The Penstock worked well. We also launched Willow on the canal as a test run for the Sponsored Walk due then on the following Monday. On the Friday (29th) there were two members of the British Public who were not glued to the television but were at Pewsham calking the few leaks that had been located. Luckily the ‘Wedding’ was re-screened that evening so that we could catch up with 'The Event' of the year.

Then on the May Bank Holiday 20 members of the work party turned out to support the Sponsored Walk either being Marshals or managing the boat trips on the new waterway. A major attraction was the mass workforce excavating the foundations for the restoration of the Wharf Wall that existed between the Spill Weir and Bottom Lock. This was alongside the towpath and could not be overlooked. Many of the walkers commented favourably on how surprised they had been on the progress that we had made during the course of the day.

Earlier in the month (14th April) we had a visiting team of 12 people from the KPMG Technology Team who had volunteered to work on a canal project at Pewsham. They chose to start the wharf wall restoration that we are now currently engaged in. As a result of their day, which they thoroughly enjoyed, they have made us a donation of £250 that was set aside for PPE which was not spent. I have said that I would keep them informed on our progress so we may get an occasional visit on site in the future.

During April our volunteers have worked a total of 702 man-hours which amounted to the sum of £9,467 in volunteer value matched funding.

 Douglas Harris

Return to top
 

 

Working Party Report — April 2011

Our volunteers have been busy again this last month working on some 22 occasions since the last Branch Meeting. Some activity has occurred almost daily by two or three members on boat repairs and on the completion of the wharf at Calne.

Since the last Branch Meeting there have been three main work parties, all held at Pewsham, and one concurrently at Calne on 13th March when the Wharf brickwork was completed.

At Calne, decorative paving was laid on 17th and final tying up and landscaping was completed on Sunday 20th March.  A fender was fixed on 24th. This comprised a 7metre length of 6”x 3” Oak timber which surprisingly took all day to fix.

The work at Calne has been well received by the good folk using the canal park which is very encouraging.

At Pewsham brickwork on the spill weir was finally completed last Sunday (10th April). This was delayed by the extra work made necessary by the damage caused by the severe winter frosts. Much of the coping brickwork had to be re-laid and the remainder re-pointed. Decorative iron fencing which will surround the structure is due to be delivered this week. This will be erected during the coming week.

The work at Pewsham has also attracted a lot of favourable comment; some people actually going out of their way to say how much they have appreciated the work that we have done over the past years. Needless to say we have presented these people with membership application forms which we hope will encourage them to join the Trust.

Repair work on Willow has continued more or less on a daily basis at Chiverlins although Mike & I recently took a 10 day break to work on another boat in Turkey.

Willow has now received a couple of top coats on the hull and we will be turning her over to work on the deck later this week.

 During March our volunteers have worked a total of 742 man-hours which amounted to the grand sum of £10,514 in volunteer value matched funding.

Douglas Harris

Return to top
 

 

Working Party Report — March 2011

More site activity since the last Branch Meeting having now held a total of 13 working events. These were held at both Pewsham and Calne with repair work concurrently, on Willow, in a shed at Chiverlins.

The weather had been generally wet only just turning dry this last week. The 13th of February was particularly wet but very good for puddling clay around a leaking small spillweir at Triangle Wood. Other places where water should not be were fixed by placing clay along the towpath and the water level reduced to stop it  overflowing the towpath. The temporary weir over the bund at Squirrel’s Rest had to be repaired as the water was beginning to wash out the sandbags. Needless to say most of the work party members looked a little grey at the end of the day and no doubt were directed immediately to the shower room on returning home.

Repair work on Willow was started on the 15th February at Chiverlins and by the end of the first week the decayed bottom had been removed. The boat was then left for the next week to dry out.

We had a clearing up day on the 27th February following the winter storms. The frost loosened bricks on the spill weir have now been removed and stacked ready for relaying when the weather improves. Tidying up the lock sites has also been started by the removal of bricks from the canal area.

This last week, the weather showing signs of turning dry, Ray Canter offered to complete the repair of the headwall of Triangle Wood culvert with the help of Dave Payne. This was completed on Friday 4th March. At times the weather felt as though it was returning to winter. It was so cold, but Friday was a lovely day and this speeded up the work which now has been completed.

Meanwhile work on Willow continued at Chiverlins and currently the boat is now half clad with new marine ply.

Our bid for funding the repair of the Wharf at Chaveywell in Calne was successful . Many thanks and congratulations to Kath for her efforts in achieving this. Work has now started on the project last Sunday, 6th March.  Ten members of the Work Party, under the guidance of Jeff Daws, cleared the area of the old wharf and laid concrete foundations for the new retaining wall. We will be continuing with the work during the current week and it is hoped to have the work substantially complete by next week.    

During February our volunteers worked a total of 442 man-hours which amounted to the sum of £5935 in volunteer value matched funding. Looks like being another busy year for the Work Party team.

Douglas Harris

Return to top

 

 

Working Party Report — February 2011

Since the last Branch Meeting, held on the 11th January, we have held three work parties, all held at Calne. In addition, on 30th January, we also worked at Pewsham.  The activity was mainly scrub clearance and general maintenance, the weather being too cold to continue with the outstanding bricklaying at Pewsham.

At Pewsham, the generally wet weather during January has filled the canal to capacity and this has put a strain on our temporary structures to manage water levels during the interim stage of the dredging. This has been exasperated by the low level of some sections of the towpath which, on occasions, has acted as temporary spillweirs. An emergency workparty team are going to Pewsham this week to lower the water level in some of the sections, repair bunds and place sandbags at points on the towpath where water tends to flood.

At Calne we have made good progress with the clearance of bramble, fallen trees & low branches over where the towpath used to be on the west side of Chaveywell Bridge. It is hoped that the general public will use this area, next to the canal, as the footpath as it much less muddy than the path that is currently used. We have also managed to remove a fallen Willow that had lain right across the canal at the Winding Hole. This would have obstructed the route of boat trips planned for Easter Saturday at the Calne Easter Bunny Hunt.

The past cold weather has damaged some of the brickwork laid in November. Such cold weather that we had in December could not have been anticipated and the damage was done before we could improve the protective cover laid over the work. Even the brickwork laid in the summer was affected.  As soon as the danger of frost recedes we will carry on with the work repointing and relaying brickwork affected. It is hoped that a week of continuous working will complete the repairs and the outstanding bricklaying work.

Kath our Director of Fundraising is tonight attending the Calne Area Board Meeting in company with Jeff Daws where our Bid for a grant to repair Chaveywell Wharf is being considered. Kath has worked hard on the bid and we should wish her every success.

 

The dismantled steelwork of the Bailey Bridge, from Frome, needs some immediate remedial work done to limit corrosion on the fixing holes of the bridge panels. Mike Lee, our Director of Engineering (West) would like a few volunteers from our Branch to help him at Outmarsh Farm, where the steelwork is stored. This is to ensure that the corrosion is limited whilst in storage. There is no need to be a member of the work party to help Mike.

During January our volunteers worked a total of 332 man-hours which amounted to the sum of £3,908 in volunteer value matched funding. Gentle beginnings of what could be a busy year for the Work Party team.

Douglas Harris

Return to top

 

 

Working Party Report — January 2011

A successful year passed and another full programme of restoration ahead of us. We will be hard pressed to do more than was achieved last year but we can consolidate our progress so far. Finishing work at Pewsham with the aim of getting an undivided stretch of water from the locks to the Reybridge end of cut would be a successful outcome.

Since the last Branch Meeting, held on the 14th December, we have held just one work party and that was last Sunday 9th January when we had an attendance of 22 members. Prior to that the Work Party Management Team met on the 4th of January and hammered out a programme which includes work at Calne, Pewsham and Semington.

There's a lot to be done at Pewsham in preparation of the final dredging and re-watering up to Bottom Lock:-

The Spill Weir coping bricks to be laid and weir board guides to be installed. This work was interrupted by the early approach of freezing weather in November but should not take more than two days to finish.

Cocklemore Brook culvert exit end structure to be repaired.

Triangle Wood Culvert exit head wall to be finished.

All to be completed before water is extended to the lock.

 

There is some remedial work to be carried out on Double Bridge including the installation of a waterproof membrane and towpath raising and widening in places; work that could all be carried out concurrently.

 

We also have a project lined up at Calne where the wharf is in need of refurbishment, and more scrub to be cleared from the canal where it is planned to extend the cut westwards.

 

If that is not enough we have been asked to restore the dismantled steelwork of the Bailey Bridge that was given to us from Frome which is to be installed over the Melksham Link near Semington.

During December our volunteers worked a total of 114 man-hours which amounted to the sum of £1,343 in volunteer value matched funding.

These hours were included in my report for last month so the Grand Total for the year ended 31st December 2010 is unaffected and remains at:- 5,847.5 man-hours which amounted to the Sum of:- £81,450.90 It was a record!

Douglas Harris

Return to top

 

 

Working Party Report — December 2010

We have held just four Work Parties since the last Branch Meeting, the last being held at Calne.

The cold weather put a stop on the bricklaying and as a consequence the work on the Spill Weir and Triangle Wood Culvert, at Pewsham, could not be completed. However we have made good progress on the scrub clearance at the Reybridge end of the cut. Progress is slower than normal as we have to haul all the tools and carry the arisings by hand to the fire site. Recently erected fences prevent our using vehicular transport on this section. With an average attendances of 14 the hand work was not too arduous. Another session on this end of the cut we should be able to clear all the scrub to which we have access. Dredging on this section however will have to wait until we have been given permission to clear the other half of the canal bed which belongs to another farmer. (the boundary between the two farms goes down the centre of the canal bed).

At Calne we carried on with the timber removal. This was cut last winter during a visit by KESCG. The canal was dry then (5th December 2009) unlike last Sunday when it was extremely boggy, It was so wet we had to lay builders planks on the ground so that we could traverse the mud with our wheel barrows. All the loose timber has now been removed and left by Chaveywell Bridge for people to take away by road trailers. It is mainly Aspen which will burn if well dried out.

There remains three large trees growing out of the canal bed which regrettable have to be felled. This will have to be done during the next two months to avoid the bird nesting season. We have been offered some free native variety trees which could be planted on the exposed canal bank. These will have to be provided with substantial tree guards and maintained for a few years if they are to survive. There are also plenty of spaces at Pewsham where trees could be planted. Ideal winter work for some.

During November our volunteers worked a total of 428 man-hours which amounted to the sum of £5,775 in volunteer value matched funding.

As we have no more work parties planned for the rest of December I can report that the total man-hours for the Year Ending 31st December is:- 5847.5 which amounts to the Grand Total of:- £81,450.90. Looks like another record to me to me.

Last year’s total was 5587 man-hours and £78,132.

Douglas Harris

Return to top

 

 

Working Party Report — November 2010

Another very busy month mainly due to the dredging which has tied up our volunteers five days a week plus all the preparation and planning. Together we have been on site held a total of 21 occasions mostly at Pewsham but we have also worked at Calne this past Sunday. As before the workload has fallen on the faithful few who have been able to attend midweek but attendances on the Sunday events have also been significant. For example 25 volunteers turned up on 31st October which included four new members. We now have a steady stream of enquiries from people wishing to join the work party ranks and we may have to consider its management to employ people effectively

Work on the spill weir at Pewsham is now complete apart for about a couple of metres of coping on the upper level. Drainage from the locks has now been diverted into the inlet duct but so far the level has not yet reached the invert.  Now that the dredging has terminated at the Squirrel’s Rest Breach the landscaping and fencing can be completed at leisure as too can the weir structure which may have to accommodate varying levels of canal water when the dredging reaches Bottom Lock, hopefully, next year.

I’ll leave references to the dredging work to Colin Fletcher the Trust’s Project Director (West) apart from saying that it was a great achievement and his leadership should be congratulated.

Work started on the repair of the headwall of Triangle Wood culvert on 26th September which had suffered some subsidence. During the past week however, with the help of our new volunteer, Ray Canter, the work including the building of two buttress walls has moved on significantly. Two more work parties have been organised for this week and I would not be surprised if the work is all but finished by the next full work party on Sunday 14th November. The towpath at the culvert has now been raised to its correct level so that the height of the structure can be determined without guesswork.

During October our volunteers worked a total of 884 man-hours which amounted to the sum of £14,012 in volunteer value matched funding. The total so far this year ending 31st December is:- £74,300. Looks like another good year to me.

Douglas Harris

Return to top

 

 

Working Party Report — October 2010

We have held a total of 10 Work Parties mostly at Pewsham but the total also includes visits to Calne & Forest Farm to carry out autumn mowing.

Work on the spill weir at Pewsham is now in the final stages with just the top and lower coping levels to complete. However the structure will be able to take flood water as the remaining work is well above maximum canal water level.

Work has started on the repair of the headwall of Triangle Wood culvert which had suffered some subsidence. Foundations of new buttress walls have been prepared and one of the concrete foundations laid.

The fencing that was taken down in the Meadow has since been reinstated which included a 15ft gate and stile for the public footpath.

On Monday work has started on the second stage of dredging at Pewsham. This is will run from Triangle Wood north towards the locks. We have less plant on site this time comprising an 8 tonne digger and two 3 tonne 4WD dumpers.

During September our volunteers worked a total of 467 man-hours which amounted to the sum of £6446.40 in volunteer value matched funding.

Douglas Harris

Return to top

 

 

Working Party Report — September 2010

We have held a total of 12 Work Parties at Pewsham since the last meeting on 10th August. Not as many as last month which, at 23, was quite exceptional. Never-the-less the restoration work at Pewsham carried on relentlessly until the week ending 20th August. Yours truly was glad to get away for two weeks holiday and now followed by Colin for what I expect was the same reason.

Work on the Pewsham Spill Weir continued with the help of our contractors until 23rd August having completed the canal side of the structure. The remaining work below the weir can continue even with partial rewatering in the canal as all the remaining brickwork will be above the proposed initial water level in the canal.

Post Pewsham Dredging, the Work Party have been busy off-site providing Boat Trips at the Chippenham River Festival on the 29th August in addition to working simultaneously at Pewsham.

The ‘Junction Site’ at Semington was cleared of bramble and long grass earlier on the 22nd in preparation for the Royal Visit on the 8th September. At the ‘The Event’ itself the Branch was well represented by a large turnout of our Branch members and volunteers. I am sure this will be covered by another report at this meeting.

Finally, at Wichelstowe, the Branch supported Swindon Branch’s event in celebrating the 200th anniversary of the construction of the Wilts & Berks Canal by providing Boat Trips in ‘Willow’ and ‘Damsel Fly’ in association with the new Trust’s Narrowboat named, “Dragonfly”, by HRH the Duchess of Cornwall last Wednesday.

During August our volunteers worked a total of 658 man-hours which amounted to the sum of £9,821 in volunteer value matched funding. Another good month even though it was the holiday season.

Douglas Harris

Return to top

 

 

Working Party Report — August 2010

We have held a total of 23 Work Parties at Pewsham since the last meeting on 13th July     (including today). Again this extreme activity relates to supporting our contractors who have been dredging the canal and rebuilding the towpath at the Double Bridge end of the cut.

The towpath north of Double Bridge turned out to be 4ft below its correct level. We knew it was low because of the survey that Martin Stubbs carried out in 2006 but now that it has been rebuilt with an 8ft track width on top the embankment looks enormous and has taken a lot of work and material to create.  The towpath in the meadow was also well below that required and the canal, now dredged, is also a lot wider than expected. The silt line as revealed when the top soil was removed was a clear indication of where the canal lay and it is thought that the width was cut to ease the navigation around the sharp bend in the canal as it follows the tight contour of the hill. 40 tonnes of roadstone has now been delivered to site to create the hard topping of the towpath created so far.

We started the repair of Cocklemore Brook culvert on Monday 19th July, putting work on the Spill weir on hold as that work could continue if the dry weather came to an abrupt end. By the following Saturday we had completed the culvert duct to entrance position and we had Robert Brotherston at Pewsham for the weekend to help with the head works and wing wall construction. By Tuesday 27th July the culvert was repaired and the team returned to the Spill Weir rebuild on Wednesday 28th July.

 The periphery wall is now complete and work has started on the weir wall and the canal side structures. This will ensure that the critical work is completed before water appears at the inlet duct following the dredging. Providing the water level in the canal is kept low work can continue on the tail race and discharge benching by our volunteers without risk of it being inundated. Hopefully we will have this completed before it is required to raise the water level and before the winter rains begin.

As you will appreciate a lot of work has been carried out the past few weeks and this is borne out by the man-hour figures worked by our volunteers. This does not include the extensive hours worked by our contractors who have been on site almost 7 days a week since the start of the project on the 5th July.

So, during July, our volunteers worked a total of 1038 man-hours which amounted to the grand sum of £15,088 in volunteer value matched funding. I doubt that we can beat that easily.

Well done those who turned out almost every day to help the project along. Their effort was much appreciated.

Douglas Harris

Return to top

 

 

  Working Party Report — May 2010

There was no report from me at the last Branch Meeting for which I apologise. However we have held 6 work parties at Pewsham since the 9th of March Meeting.

Boat trips were run with ‘Willow’ at Calne on the 3rd March for the Easter Bunny Hunt and, at Foxhangers on the 29th, we carried out some maintenance on ‘Damsel Fly’ in preparation for a Helmsman training session on the 30th April. We had 10 ‘students’ on this day practicing boat manoeuvres with the electric outboard motor and the Mariner engine, that we normally use.

At Pewsham the continuing strategy is to clear the trees and roots within the canal bed and structures These are  part of the major restoration project for this year.

Work on the Spill Weir has started and already bricklaying has begun to take shape around the culvert opening. Additional roots identified as being in the path of the required brickwork have been also removed. It is surprising how much timber was embedded in and around the old structure. There is still one significant root to be removed but this is not interfering with the bricklayers—as yet!   

At Triangle Wood the large Oak tree standing alongside the culvert has been totally removed as has also the large Ash tree that was close by to the south. Tim has started clearing porous soil away from the culvert but the canal bed was too soft for our newly acquired  4x4 dumper to operate. It was still too soft last Sunday so Tim assisted the Tirforing gang in their attempt to remove the two Ash stumps from the canal bed in the meadow. One stump has proved to be extremely difficult to shift and may only succumb to a full excavation or even a power winch - which we have not got.

At Calne, on the 2nd May, there was an attempt to mow the canal area but the weather was too wet and the event was cancelled. I hope to get this done during the week.

During the whole of  March our volunteers, worked a total of 444 man-hours which amounted to £6,203 and in April 355 hrs were worked amounting to £4,210 in volunteer value matched funding.

 

Douglas Harris

Return to top

 

 

  Working Party Report — March 2010

We have held 5 working parties since the last Branch Meeting—all at Pewsham.

The main thrust has been the clearing of the large trees growing out of the canal structures that are the subject of the restoration planned for this year.

The large Ash tree by the spill weir finally was removed on the 28th February when we had our maximum attendance so far - 21 volunteers. Needless to say not all 21 were employed at the Spill Weir and several other small trees that were in the canal or interfering with passage along the towpath were also removed. Other work included digging of trial holes in the in-filled section of the canal north of Double Bridge which is also scheduled for re-excavation.

The removal of the Ash tree now clears the way for us to start the Spill Weir restoration.

Re-puddling work on the Triangle Wood culvert depends upon the successful removal of the Oak tree standing alongside which hopefully will be achieved this coming Sunday.

During the whole of February our volunteers, worked a total of 386 man-hours which amounted to £4799 in volunteer value matched funding.

In future the matched funding hours will be identified with the work associated with its respective funding.

 

Douglas Harris

Return to top

 

 

  Working Party Report — February 2010

Just one work party since the last Branch Meeting but a significant one never-the-less as on the 31st January the team started the scrub clearance on the canal where it crosses the A4 road at Pewsham. The aim of this was to advertise the presence of the canal to the passing public. Wiltshire Council through the good offices of the Canals Officer, Ken Oliver, erected an official sign on the verge indicating that this was the Wilts & Berks Canal.  I was not able to attend being away in sunnier climes but 18 members of the team were and did a magnificent job in about 4 hours—without me.

With the good news of Kath’s success with funding applications we can look forward to a busy Spring & Summer. Some of the funding has to be spent by the end of March so as soon as the weather becomes a bit more open we will begin the rebuilding of the main spill weir below Bottom Lock. In the meantime we have to clear the remains of the large Ash tree that was growing out of the masonry and all the displaced brickwork.

Following that, the repairs to the two remaining culverts below Bottom Lock have to be completed and puddled before we can begin the dredging.

At Calne there remains the clearance of the towpath to do which we hope to complete during the coming weeks. Also the Castlefields Canal & River Park Association (CARP) are well on their way to securing funding for the rehabilitation of the lock and have passed Stage 1 of the their application. Together with ourselves in the Trust and CARP we have to convince the ‘Facilitator’ that we can complete the Project. One of the benefits of this work, apart from an improvement in the appearance of the lock, is that more water may be extracted from the River Marden, when permitted by the Environment Agency, which will refresh the water in the canal near the lock. It will also enable us to re-water further extensions of the canal with confidence.

All very exciting stuff.

During the whole of January the team, worked a total of 212 man-hours which amounted to £2587 in volunteer value matched funding. Not bad for starters.

Douglas Harris

Return to top

 

 

  Working Party Report — January 2010

There have been just two work parties since the last Branch Meeting on the 8th of December. This was mainly due to the Festive Season and a request from the farmer on whose lane we use to gain access to the Pewsham site.

One meeting was held at Calne on the 13th December, where the team enjoyed a well earned 'Mulled Wine & Mince Pie Bonfire', and the other last Sunday, 10th January 2010, at Pewsham in Artic conditions. What a contrast in the weather conditions.

The event at Calne was photographed by Justin Guy our Press Officer. The picture taken at site has subsequently appeared all the local papers. It must have been something to do with having our Chairman beaming happily in the foreground or possibly my unfortunate absence. Never-the-less it was very good publicity.

Last week we were to hold a midweek meeting at Pewsham on the 6th January but weather conditions were difficult, to say the least, so we met in the Red Lion at Lacock instead to discuss our future plans and the necessary funding. It's not all work on our work parties.

Last Sunday seven of the gang turned out on a bitterly cold morning and managed to clear the remaining tree tops and logs from the canal left by the tree surgeons in October. Some of the logs required three people to lift them. Ideal work for ‘Gorillas’ really. We also had a very nice bonfire.

During December the team, worked a total of 543 man-hours which amounted to £8635 in volunteer value matched funding. The total for whole year ending 31st December amounted to £78,132 which has totally smashed last year's total of £51,811. Well done team.

Are we going to do this again this year?

Douglas Harris

Return to top