|
The Melksham, Calne and
Chippenham Branch |
|
Previous Work Party Reports |
|
Working Party Report —
May 2010
There was no
report from me at the last Branch Meeting for which I
apologise. However we have held 6 work parties at Pewsham
since the 9th of March Meeting.
Boat trips were
run with ‘Willow’ at Calne on the 3rd March for the
Easter Bunny Hunt and, at Foxhangers on the 29th, we carried
out some maintenance on ‘Damsel Fly’ in preparation
for a Helmsman training session on the 30th April. We
had 10 ‘students’ on this day practicing boat manoeuvres
with the electric outboard motor and the Mariner engine,
that we normally use.
At Pewsham the
continuing strategy is to clear the trees and roots within
the canal bed and structures These are part of the major
restoration project for this year.
Work on the
Spill Weir has started and already bricklaying has begun to
take shape around the culvert opening. Additional roots
identified as being in the path of the required brickwork
have been also removed. It is surprising how much timber was
embedded in and around the old structure. There is still one
significant root to be removed but this is not interfering
with the bricklayers—as yet!
At Triangle
Wood the large Oak tree standing alongside the culvert has
been totally removed as has also the large Ash tree that was
close by to the south. Tim has started clearing porous soil
away from the culvert but the canal bed was too soft for our
newly acquired 4x4 dumper to operate. It was still too soft
last Sunday so Tim assisted the Tirforing gang in their
attempt to remove the two Ash stumps from the canal bed in
the meadow. One stump has proved to be extremely difficult
to shift and may only succumb to a full excavation or even a
power winch - which we have
not got.
At Calne, on
the 2nd May, there was an attempt to mow the canal area but
the weather was too wet and the event was cancelled. I hope
to get this done during the week.
During the
whole of March our volunteers, worked a total of 444
man-hours which amounted to £6,203 and in April
355 hrs were worked amounting to £4,210 in
volunteer value matched funding.
Douglas Harris |
Return to top |
|
Working Party Report —
March 2010
We have held 5
working parties since the last Branch Meeting—all at
Pewsham.
The main thrust
has been the clearing of the large trees growing out of the
canal structures that are the subject of the restoration
planned for this year.
The large Ash
tree by the spill weir finally was removed on the 28th
February when we had our maximum attendance so far - 21
volunteers. Needless to say not all 21 were employed at the
Spill Weir and several other small trees that were in the
canal or interfering with passage along the towpath were
also removed. Other work included digging of trial holes in
the in-filled section of the canal north of Double Bridge
which is also scheduled for re-excavation.
The removal of
the Ash tree now clears the way for us to start the Spill
Weir restoration.
Re-puddling
work on the Triangle Wood culvert depends upon the
successful removal of the Oak tree standing alongside which
hopefully will be achieved this coming Sunday.
During the
whole of February our volunteers, worked a total of 386
man-hours which amounted to £4799 in volunteer
value matched funding.
In future the
matched funding hours will be identified with the work
associated with its respective funding.
Douglas Harris |
Return to top |
|
Working Party Report —
February 2010
Just one work
party since the last Branch Meeting but a significant one
never-the-less as on the 31st January the team started the
scrub clearance on the canal where it crosses the A4 road at
Pewsham. The aim of this was to advertise the presence of
the canal to the passing public. Wiltshire Council through
the good offices of the Canals Officer, Ken Oliver, erected
an official sign on the verge indicating that this was the
Wilts & Berks Canal. I was not able to attend being away in
sunnier climes but 18 members of the team were and did a
magnificent job in about 4 hours—without me.
With the good
news of Kath’s success with funding applications we can look
forward to a busy Spring & Summer. Some of the funding has
to be spent by the end of March so as soon as the weather
becomes a bit more open we will begin the rebuilding of the
main spill weir below Bottom Lock. In the meantime we have
to clear the remains of the large Ash tree that was growing
out of the masonry and all the displaced brickwork.
Following that,
the repairs to the two remaining culverts below Bottom Lock
have to be completed and puddled before we can begin the
dredging.
At Calne there
remains the clearance of the towpath to do which we hope to
complete during the coming weeks. Also the Castlefields
Canal & River Park Association (CARP) are well on their way
to securing funding for the rehabilitation of the lock and
have passed Stage 1 of the their application. Together with
ourselves in the Trust and CARP we have to convince the
‘Facilitator’ that we can complete the Project. One of the
benefits of this work, apart from an improvement in the
appearance of the lock, is that more water may be extracted
from the River Marden, when permitted by the Environment
Agency, which will refresh the water in the canal near the
lock. It will also enable us to re-water further extensions
of the canal with confidence.
All very
exciting stuff.
During the
whole of January the team, worked a total of 212
man-hours which amounted to £2587 in volunteer value
matched funding. Not bad for starters.
Douglas Harris |
Return to top |
|
Working Party Report —
January 2010
There have been
just two work parties since the last Branch Meeting on the
8th of December. This was mainly due to the Festive Season
and a request from the farmer on whose lane we use to gain
access to the Pewsham site.
One meeting was
held at Calne on the 13th December, where the
team enjoyed a well earned 'Mulled Wine & Mince Pie
Bonfire', and the other last Sunday, 10th January
2010, at Pewsham in Artic conditions. What a contrast in the
weather conditions.
The event at
Calne was photographed by Justin Guy our Press Officer. The
picture taken at site has subsequently appeared all the
local papers. It must have been something to do with having
our Chairman beaming happily in the foreground or possibly
my unfortunate absence. Never-the-less it was very good
publicity.
Last week we
were to hold a midweek meeting at Pewsham on the 6th
January but weather conditions were difficult, to say the
least, so we met in the Red Lion at Lacock instead to
discuss our future plans and the necessary funding. It's not
all work on our work parties.
Last Sunday
seven of the gang turned out on a bitterly cold morning and
managed to clear the remaining tree tops and logs from the
canal left by the tree surgeons in October. Some of the logs
required three people to lift them. Ideal work for
‘Gorillas’ really. We also had a very nice bonfire.
During December
the team, worked a total of 543 man-hours which
amounted to £8635 in volunteer value matched funding.
The total for whole year ending 31st December
amounted to £78,132 which has totally smashed last
year's total of £51,811. Well done team.
Are we going to
do this again this year?
Douglas Harris |
Return to top |
|
Working Party Report — November 2009
There have been
8 occasions where members have been working on site. I am
not calling these work parties this time as some were only
attended by one or two, such as at Calne this past weekend
when we were hosts to a visiting group of volunteers from
the Kent & East Sussex Canal Restoration Group (KESCRG).
Such is the attraction of working at Pewsham. More on this
later.
At Pewsham the
task of clearing Middle Lock has continued. It has been hard
going, wet and mucky most of the time but the team have made
good progress. We are about ¾ the way through to total
clearance. Then only two more to go. But there may be a
better way!
Down at the
Reybridge end of the section six members of the team have
been busy erecting a post and wire fence along the towpath
to restrain Messr’s. Doel’s cattle from going walkabout
along the towpath. This took part on two mid-week occasions
finishing on Friday 30th October when Colin and I finally
strained the wire.
On Friday 23rd
October we had a team of tree surgeons on site to fell three
large trees that were growing on or interfering with canal
structures. This job took all day and was completed with
only minor collateral damage. We have been clearing tree
tops and logging the timber ever since.
Mowing has
progress slowly by the few who see this as a better option
to lock clearance. It’s a strenuous and sometimes tedious
job which when done in the late Spring seems a waste of time
as it grows back again so quickly but, believe me, it does
make the Autumn mow much easier. If, as was the case last
year, parts were missed altogether, the task is sometimes
like scrub clearance all over again. So it has to be done.
Our fund raising team are working on ways to provide some
more exotic machinery to speed up the process.
At Calne KESCRG
were given access to Mrs Sutton’s land at the western end of
the re-watered cut. Here the scrub resembled a jungle but
over the past weekend the visitors made short work of all
but the largest trees. They are coming back this way again
on the weekend of 5/6 December to start clearing the scrub
from the canal at the A4 crossing (by the SAAB Garage).
Their forestry team will initially return to Calne to fell
the large trees left standing then come to Pewsham. KESCRG
may even come back again on the 12th & 13th December to
Pewsham when we might persuade them to look at the locks as
well.
During October
the team worked a total of 342 man-hours which
amounted to £4639 in volunteer value matched funding.
The total for the year so far has reached £62,125
which looks as though this might be a record year.
Douglas Harris |
Return to top |
|
Working Party Report —
October 2009
There have been
10 work parties since the last Branch Meeting held on the
8th September. Six of these were held at Pewsham two at
Forest Farm and two at Calne.
At Pewsham the
task of clearing Middle Lock has continued. It has been hard
going as the material in the lock chamber is full of broken
bricks and steelwork from the gates. But we are making
progress - sometimes in spite of poor weather.
We have also
started the autumn mowing and are now about halfway along
the whole section. Some parts have not been cut for more
than a year because of the previous wet state of the canal
bed last year. The mowing here has been difficult and
indicates that we should ensure at least one cut is made
during each year.
At Calne we
have tidied up the wharf area by Chaveywell Bridge, mowed
the whole length and pulled timber from the water that had
been blown down during the past gales. On Town Lock some
additional exploratory excavation has been undertaken at the
site of the upper gate so that the extent of existing
masonry can be determined.
The CARP
organisation are lending their good offices to seek further
funding for the completion of the lock rehabilitation. This
is not restoration as a navigavable structure but in
appearance it will look like a lock complete with gates. It
will, however, have a large diameter pipe laid along the
whole length of the chamber which will convey water from the
River Marden to the canal. This will significantly improve
the water quality.
At Forest and
Queenfield Farms we have made up for last year’s neglect and
mowed the whole section thoroughly.
Attendances
have still be good, usually above 10 on the Sundays. On the
23rd August 19 turned up which included a photo shoot of the
‘big cheque’ representing the proceeds of the Sponsored walk
earlier this year.
During
September the team worked a total of 362 man-hours
which amounted to £4760 in volunteer value
matched funding.
I am sorry that
no report was given in my absence at the last Branch
Meeting. However, for the record, during August there were
two work parties, both at Pewsham, clearing Middle lock.
They worked 279 man-hours which is valued at £3903. We also
held a work party management meeting at my house. A revised
work programme was put forward but, during my absence,
restrictions on our access to the Pewsham Site, has put this
on hold for a while.
Douglas Harris |
Return to top |
|
Working Party Report —
August 2009
There have been just three
work parties since the last Branch Meeting, again held at Pewsham.
At both the main thrust has
been the clearance of Middle Lock including the stump of the large Oak
tree growing in the lock.
Without mechanical
assistance progress has been slow but not because of lack of effort. The
stump proved resistant to the end when it was finally removed last
Sunday. The return of wet weather has put the repair of Cocklemore Brook
culvert on hold for a while and we are hoping for a return to drier
weather before the summer ends so that we can continue with the repairs.
On Wednesday 29th July a
small party surveyed the brook downstream of the culvert to see if it
was possible to permanently lower the water level. This will help with
access for the repairs and provide a permanent scouring to keep the
culvert free of silt. It was found that dredging would greatly improve
conditions at the culvert. This work has to be agreed with the farmer.
Attendance has been good
even with summer holidays taking their toll. Despite the good
attendance, working normally on only two days each month does not see
much progress over the year and there is an ever increasing amount of
restoration to do not forgetting maintenance of those parts completed.
The Work Party Management
Team are considering introducing more working periods each month. This
could be achieved by working each Sunday with possibly different people
and another dedicated team leader, mid week work parties for mainly
maintenance work (for the retired amongst us) or working 2, 3,or even 4
day weekends where a specific task is to be undertaken. This option
would be desirable where extra plant has to be hired. The ‘management
team’ hope to meet shortly to discuss these options and would welcome
suggestions from the workers.
During July the team worked
a total of 442 man-hours which amounted to £7,388 in
volunteer value matched funding. Not bad for normal working.
Douglas Harris |
Return to top |
|
Working Party Report —
July 2009
There have been 11 work parties
since the last Branch Meeting, on 9th June, all held at Pewsham. The large
number was primarily due to our hosting a week long camp from Waterways
Recovery Group where we provided experienced digger and dumper drivers as
supporting effort.
The main task was the clearance
of Top & Middle Lock but the wet ground at Top Lock prevented much removal
of the sediment. However many items of ‘archaeological’ interest were
extracted and left alongside for any ‘collectors’ to take away should they
wish. Otherwise we shall have to take it all up to the tip—eventually.
Attendance at our normal work
parties remains high topping 19 on the 14th June. New volunteers continue to
join us which is very encouraging.
There has been a slight air of
anticlimax following the high of the official opening of Double Bridge by
HRH The Duchess of Cornwall; but this could be cured by the queue of
exciting restoration jobs coming over the horizon.
The first is the clearance of
all three locks which has been kick-started by the WRG Camp. This work is
necessary for us to establish the extent of damage caused by the demolition
practice during WW2 so that detailed estimates for their restoration can be
obtained.
The dry summer (so far) has
provided us with a window of opportunity to get at the damaged masonry of
Cocklemore Brook Culvert. Our workparty will be carrying on with the work
which has been started by WRG but we will have to hurry as the current low
water level may not last. I am thinking of weekly, if not midweek,
workparties to speed the job along. Our experience with Double Bridge has
shown how the momentum can be maintained by having just a few volunteers
working extra days between the main work parties.
The large spill weir at Bottom
lock is another project that can be started this Autumn but unlike
Cocklemore Brook Culvert is not so critical on the water table.
Finally there are the towpath
repairs that will be necessary if we are to fill the rewatered sections to
capacity. However I cannot get too excited about this job until the funding
is in place.
During the last month (June)
the team worked a total of 315 man-hours which amounted to £4,302
in volunteer value matched funding. Not as much as for May but so far
this month we have clocked up another 333 man-hours. Watch this space for
this month’s total.
Douglas Harris
|
| Return to top |
|
Working Party Report — May 2009
|
|
Working Party Report — April 2009
|
|
Working Party Report — March 2009
The next was held on 22nd February with another record turnout of 18. Here the team made good progress in clearing scrub from the southern extension of the Naish Hill pound. We also moved the fresh delivery of clay down to the culverts to be backfilled. By the end of the day all the scrub and arising at the southern end of the new section had been cleared and the site left clean and tidy. At the Bridge, footings were laid for the rebuild of the north far-side wing wall. Martin and Mario started the delicate task of replacing decayed brickwork under the arch. Another midweek work party was held on Wednesday 25th. The aim was to mow the canal surroundings adjacent to Double Bridge and to prepare for more bricklaying. Either the job description was unappealing or the weather was not inviting because we only had three turn up with another two coming to see us working at lunchtime. We did what we set out to do and had a good time. Even our Chairman came to see us, afterwards – in the pub! We followed up the mowing with another ‘spur-of-the-moment’ work party meeting at Bell beforehand this time to make sure of some lunch. The weather was perfect and Colin & I managed to brush cut the towpath edges from where we finished on the 25th to the Winding Hole. This part of the towpath had not been cut for more than two years and was overhanging the cycleway in places, whereas the remainder, up as far as the locks, had, and was looking reasonably well cared for. Finally on Sunday 8th March another massive party of 18 turned out in what eventually became a thoroughly miserable cold and wet day. It was so promising in the morning and the team soon got cracking on the Bridge, the final site clearance and burning all the available cut brushwood in the winding hole. But by lunchtime the rain had arrived accompanied by strong winds which was OK for the bonfire people but not quite so good for the Bridge team or those trying to move on the slippery towpath surface in the southern end of the Naish Hill section. Tim had brought his digger to start laying puddle clay in the Naish Hill culvert but no sooner had he got himself nicely in the canal bed to start placing the clay when the rain came so he prudently extracted himself before getting permanently stuck. For the month of February we worked another 377.50 man-hours which amounted to £4741 in volunteer value matched funding.
Douglas Harris
|
Working Party Report —
February 2009
The first Work Party since
the last Branch Meeting was held at Calne on Thursday 22nd January,
nominally to repair the post & rail fence around the partially restored
lock. This had been attacked by vandals and required 7 new rails to put
it right.
While we were on site the
wharf was cleaned up and grass growing up through the paving removed. A
general inspection showed that there was much debris in the canal,
natural and also manmade which will need removing before we can run boat
trips there again at Easter. Also a large Willow had fallen right across
the canal and the path running through the Bowood Wild Life area west of
Chaveywell Bridge. While we were there we were able to remove the tree
top which had blocked the path.
Then on Sunday the 25th
January the full team of 16 volunteers turned out at Naish Hill to
continue scrub clearing on the southern end of the pound. It had rained
earlier overnight and made the ground very slippery once again. It was
difficult just to walk let alone haul the timber and scrub to the two
bonfires we had burning. In spite of the conditions all the cut scrub
laying on the towpath was finally removed and burnt. Much of the
material in the canal was cleared as well.
Finally on the 8th February
15 of us turned out in what started out as a pleasant day, on clean snow
covered ground. We cleared timber in the vicinity of the site of the
lift bridge and also at the far southern end of the cut.
It proved to be quite a
challenge to get the tractor, trailer and the dumper along the snow &
ice covered towpath. The tractor had to be pushed whenever there was a
slight incline and it was also difficult to keep the dumper on the track
as yours truly found out.
Unfortunately the weather
deteriorated during the afternoon which left us a little damp by the end
of the day. It could have been a lot worse remembering yesterday’s
weather.
For the month of January we
recorded 320 man-hours which amounted to £5266 in
volunteer value matched funding.
Looks as though we are
getting off to a good start this year.
Douglas Harris
Working Party Report —
January 2009
We have been on site four
times since the last Branch meeting—all at Pewsham.
The first held on the 14th
December. This being the last before Christmas we celebrated by having
mulled wine and mince pies with our lunch. These were generously donated
by our chairman and some of our more noble members for which the team
were very grateful. The day, I recall, was rather damp & dull and the
work in clearing scrub from the southern section of the Naish Hill pound
was not uplifting but, surprisingly, after lunch work resumed with a
greater gusto and by the end of the day a large amount of the towpath
was cleared.
The ground was very mucky
due to the prevailing wet weather we had to haul all the cut scrub to
the bonfire by hand. The ground was too slippery to use our dumper. The
volunteers besides covering themselves in glory by working in such
conditions also got well covered in mud.
The next work party was held
soon after Christmas on the 28th December when a few of the stalwarts
carried on with the work again making good progress. Yours truly was not
able to attend this time and it was noted that progress was quite
unaffected.
We had another midweek site
visit on the 2nd January to take delivery of some 300 old bricks kindly
donated by one of our members. These were stacked by Double Bridge ready
for the Spring bricklaying season.
Finally on the 11th January
we finally completed the scrub clearance on the towpath over the whole
length of the new work. The ground was still frozen from the past cold
weather and timber that was half submerged in the canal had to be cut
off where it lay and left to thaw out. As the weather had become warmer
the surface of the ground was as sticky as ever and we had to be very
careful not to slip. All that now remains is to remove the remaining
arising to a suitable site for burning. A remarkable achievement is such
a short time.
For the month of December we
recorded 213 man-hours which amounted to £2,584 in
volunteer value matched funding.
The final total for the year
ending 31st December 2008 was 3992 man-hours worked which was
valued at £51,811.80.
This was well up on last
year when the total value earned in 2007 was £39,302. The increase is
due to the significant larger average attendance at work parties and the
employment of skills that command a higher rate of ‘pay’.
Well done everybody.
Douglas Harris
Working Party Report —
December 2008
We have been very busy
since the last Branch Meeting on the 11th November, having held six work
parties, all at Pewsham.
The first party was a mid
week affair on Wednesday the 19th when we salvaged old bricks, scattered
near Middle Lock, for use on the wing walls and towpath under Double
Bridge. With three dumper loads we probably salvaged enough to complete
the job. During the day we also took delivery of road stone and building
sand.
The following Wednesday
26th November we laid two 150mm dia. pipes across the towpath/cycleway;
one to drain the canal in Messrs Doel’s land and another near the
winding hole, both to prevent the adjacent towpaths from being
periodically flooded. Tim brought his digger along to ‘help’ with the
excavation. Even then it was nearly dark before we were finished.
A good turnout on both
these days having 10 volunteers on the 19th and 7 on the 26th.
This last event was
followed up with a short visit by Colin & myself on Friday 28th to
re-erect the post and rail fence by the Doel’s section which we had
disturbed to lay the pipe. I recall, whilst my back was turned in
hammering nails into the rails, that I had commented aloud to Colin
(holding the rail) how few people there had been on this day, being
particularly pleasant, when someone passed by and stopped to
congratulate us on the work had we had done. We have received many
comments of support which is very gratifying.
On the weekend of 29th &
30th we had a two day session. On the Saturday concrete backfill was
laid against the new brickwork and old bricks cleaned while others moved
the remaining puddle clay down to the so-called ‘Rill Culvert’ just
south of the bridge.
On the Sunday more
brickwork was completed to bring the bridge towpath wall up to the
coping stone level for 80% of its length. The remainder of the team laid
puddle clay over Naish Hill culvert (a very mucky job I recall) whilst
the sensible ones cleared more scrub from the towpath on Messrs Doel’s
land and enjoyed a bonfire. We had a total of 5 volunteers on the
Saturday and 14 on the Sunday.
Finally, last Saturday 6th
December, Tim brought his digger and laid puddle clay over the Rill
Culvert and completed the work to 300mm below bed level. All that
remains here is to lay the remaining puddle clay when more is delivered.
For the month of November we recorded 400 man-hours which amounted to
£5,165 in volunteer
value matched funding.
Douglas Harris
|
Working Party Report — November 2008
|
| Working Party Report — October 2008 |
|
Douglas Harris |
Back to top |